Stamford Bridge Tilting Weir
The Brief
Over recent years, the Environment Agency identified the need for replacement of the existing weir penstock at Stamford Bridge. AMCO Construction enlisted the expertise of Aquatic Control Engineering Ltd (ACE) to devise and implement an effective solution.
Challenges included the weir’s location in a residential area demanded aesthetic improvements. An enhancement of operational efficiency was a key objective. Future maintenance considerations required careful planning.
The Solution
Innovative Tilting Weir Technology:
To address the aesthetic concerns and operational efficiency, ACE proposed the installation of a Tilting Weir. Unlike traditional weirs, the Tilting Weir is driven from one side, eliminating the need for an access gantry across the river. This not only improved the visual appeal in the residential setting but also significantly reduced the build-height compared to the original sluice.
Bespoke Stoplog Frames for Maintenance:
Considering future maintenance requirements, ACE designed and provided a set of bespoke stoplog frames. These frames were specially crafted to interface with a curved and sloping wall, minimizing the need for extensive concrete works within the watercourse. This bespoke solution aimed to streamline and simplify any future maintenance activities.
The Result
Enhanced Aesthetics and Operational Efficiency:
The implementation of the Tilting Weir brought about a notable improvement in both aesthetic appearance and operational efficiency. The innovative design, driven from one side, not only met the residential aesthetic expectations but also ensured a more streamlined and efficient sluice operation.
Streamlined Maintenance Access:
The bespoke stoplog frames successfully addressed the challenge of future maintenance. The specially designed frames provided an efficient solution for any required maintenance activities, interfacing seamlessly with the unique curved and sloping wall of the watercourse.
Achievements
01
Long-Term Collaboration
The Stamford Bridge project marked another milestone in the longstanding collaboration between ACE and AMCO Construction. Having successfully delivered multiple projects over the past decade throughout the UK, this project underscored the effectiveness of the ongoing partnership.
02
Innovation in Water Management
The adoption of the Tilting Weir technology showcased ACE’s commitment to innovative solutions in water management. The project not only met its immediate objectives but also contributed to the advancement of efficient and aesthetically pleasing water control structures.
03
Community and Environmental Considerations
By addressing the aesthetic concerns in a residential area, ACE demonstrated a commitment to community and environmental considerations. The Tilting Weir not only fulfilled technical requirements but also aligned with the need for harmonious integration with the surroundings.
04
Teamwork
The Stamford Bridge Tilting Weir project stands as a testament to effective collaboration, innovative engineering, and the successful integration of aesthetic and operational considerations. The ongoing partnership between ACE and AMCO Construction continues to contribute to advancements in water control infrastructure.